PJM Interconnection a Good Fit for Merchant Wholesale Generator

COVERT, Mich. – New Covert Generating Company, LLC, owner of a merchant power plant near Covert, Michigan, plans to directly interconnect the 1,100-megawatt plant with the PJM Interconnection market by June 2016, pending construction of a substation, a 345-kilovolt (kV) transmission line and transmission system upgrades.

New Covert cleared capacity in PJM’s Reliability Pricing Model auction in May 2013 and May 2014.

The Covert plant is a highly efficient, natural gas-fueled combined-cycle facility that began commercial operation in 2004. Its three independently dispatched power blocks currently produce electricity for the Midcontinent Independent System Operator (MISO) power grid.

“PJM is a good fit for merchant wholesale generators such as New Covert. It has a balanced, forward-looking capacity market that should provide certainty for covering the facility’s fixed costs,” said Brad Heisey, senior vice president of Tenaska Capital Management, LLC (TCM). “The Tenaska organization has nearly 30 years of experience in building, owning and operating power plants, experience which forms the foundation of our ability to identify and execute on complex opportunities such as those at the Covert plant.”

New Covert Generating Company is a private equity investment managed by TCM.

Construction began in August on the new interconnection facilities, which will include the new Segreto substation and a transmission line, as well as transmission system upgrades. The substation will be less than one-half mile from the Covert plant and will provide the interconnection to PJM’s transmission system. The new 345-kV transmission line will run from the Segreto substation to the Covert plant. The transmission line ultimately will be owned, operated and maintained by ITC Interconnection LLC, an indirect subsidiary of ITC Holdings Corp. (NYSE: ITC).

The new Segreto substation, new transmission line and the transmission system upgrades are all expected to be completed by spring 2016 to allow Covert to meet its capacity obligations to PJM beginning June 1, 2016.

New Covert and its affiliates are overseeing engineering, design and construction of the Segreto substation, and ITC Interconnection LLC is providing the same project management oversight for the transmission line. Burns & McDonnell has been selected as the engineering, procurement and construction contractor for the substation, as well as the transmission line.

About New Covert Generating Company, LLC

New Covert Generating Company, LLC is a private equity investment managed by Tenaska Capital Management, LLC (TCM). TCM, an affiliate of Omaha, Nebraska-based Tenaska, is a leading manager of energy private equity investments. TCM has approximately $3.5 billion in total assets under management and targets investments in oil and natural gas midstream, energy services and power generation. For more information, visit www.tenaskacapital.com or www.tenaska.com.